D & D Estimates: Metal Forming Facility
370
Building 370, located in LANL's S-Site
was a 19,594 sq/ft concrete structure built
during the 1950's and was used in the process of
forming and pressing metal.
Contaminants included: Lead Paint,
Asbestos
Q Consulting Estimate: $1,436,913.00
Contractor Bid: TBD
% of Variance:
Before demolition, lower dock:
Upper dock:
Inside:

Demolition almost complete:

Pictures and facts are
courtesy of LANL |